References.

Our reference projects include a large number of different large-scale photovoltaic plants throughout Germany. Further extensive projects are immediately before the execution. In total, our pvwerk GmbH team has so far implemented solar parks with a total output of more than 2,220 MW - on e.g. conversion areas, in industrial estates and on agricultural land.

  • 308 realized photovoltaic plants
  • Total output of more than 2.220 MW
  • In a total of 10 federal states
  • On a wide variety of sites

Project overview 

From north to south: pvwerk GmbH realizes solar parks throughout Germany. In doing so, we install plants from 1 to 100 MWp.

  • Germany-wide
  • 308 projects
  • 2,220 MW
  • Since 2011
.

(for detailed information please use our interactive map).

Solarpark Gaarz

We realized the large-scale photovoltaic project in Gaarz (near Plau am See) with a capacity of 91 MWp on an area of about 91 ha. Thereby we were responsible for all steps of the construction phase - from the realization of the area preparation, the installation of the solar park up to the laying of the route cable to the grid connection point. 

  • 91 MWp ground-mounted photovoltaic plant
  • More than 273,000 modules
  • Route distance of approx. 29,000 m 
  • 3,612 tons of steel used
.

Solarpark Zeithain

On the site of the Zeithain Industrial Park in Saxony, we built a modern solar park with a total output of 72.5 MWp. The construction process was divided into different sections and posed a challenge in that the conversion area was heavily covered with explosive ordnance residues. In addition, large-scale concrete foundations had to be made.

  • 72.5 MWp ground-mounted photovoltaic plant
  • Ammmunition clearance over the entire area
  • More than 257,000 modules
  • Road length of approx. 8,735 m
  • 3,628.9 tons of steel used

Solar Park Neuhardenberg, Airfield

Despite a relatively short construction period and obstacles such as explosive ordnance residues, we were able to realize a ground-mounted PV plant on the 240 ha site of the former military airfield Neuhardenberg, Brandenburg. With a total output of 72.3 MWp, the solar park was implemented and connected to the grid in just 6 weeks of construction.

  • 72.3 MWp ground-mounted photovoltaic plant
  • Ammunition clearance on over 240 ha
  • Construction time of 6 weeks
  • More than 298,000 modules
  • Trace length of approx. 16,000 m
  • 3,615.6 tons of steel used
.

Project Parsberg

This project included the implementation and connection of various solar parks in the area of Bavaria. With the help of the construction of an extensive route network, these could be connected to the Parsberg substation. 

  • A total of 6 solar parks
  • More than 191,000 modules
  • Route distance of approx. 15,285 m
  • 2,768.6 tons of steel used
.