Despite a relatively short construction period and obstacles such as explosive ordnance residues, we were able to realize a ground-mounted PV plant on the 240 ha site of the former military airfield Neuhardenberg, Brandenburg. With a total output of 72.3 MWp, the solar park was implemented and connected to the grid in just 6 weeks of construction.
- 72.3 MWp ground-mounted photovoltaic plant
- Ammunition clearance on over 240 ha
- Construction time of 6 weeks
- More than 298,000 modules
- Trace length of approx. 16,000 m
- 3,615.6 tons of steel used